- Project, date, report number
- One report per day per job. Number them so a missing day is obvious.
- Weather
- Conditions at start and end of day. Weather is the most common cause of delay claims.
- Manpower
- Each company and trade on site, the crew, headcount, total hours, and the cost code and area they worked. Include subcontractors.
- Work performed
- What was done, where, and how much: quantity installed and its unit, against the schedule activity and cost code.
- Equipment
- Equipment on site, operating and idle hours, the operator, and any deficiency.
- Materials and deliveries
- What arrived, from whom, how much, the delivery ticket number and where it was put.
- Inspections and tests
- Who inspected what, against which spec section, the result and any corrective action.
- Quality control
- Preparatory, initial and follow-up inspections, deficiencies found, and who is responsible.
- Safety observations
- Toolbox talk topic, hazards seen, and the action taken. Record incidents separately too.
- Delays and disruptions
- The cause, what it affected, hours lost and what you did about it. Be specific and factual.
- Visitors
- Name, organisation, purpose, and arrival and departure times.
- Instructions and coordination
- Directions received, who gave them, and the RFI, drawing or change reference. Note verbal directions here the same day.
- Signature
- Whoever wrote the report signs and dates it. Don't edit a signed report; add a dated correction.